Sheeting the Garage
Work began this week on sheeting the garage. Because the walls are higher than 8 feet it had to be done in two
sections. The lower portions as can be seen in this photo are simply covered with 4x8 sheets of 1/2" OSB.
Thank God for nail guns. Using a nail gun saves an incredible amount of time when there's a lot of nailing to
be done. When installing exterior sheeting it helps to have someone on the inside to let you know if you miss
hitting the studs in the center of the sheet. Too many misses and the building inspector won't be happy.
As I said earlier the walls were too tall to do in one section. The top 3 1/2 feet were done separately once
the entire garage lower portion was finished.
Because these walls top out a little over 13 feet scaffolding was used to make sheeting the top section easier.
This is the shop or working section of the garage. To give it some scale, the window on the far wall is 4
feet wide.
After the entire garage is sheeted we needed to start on the gable ends in preparation for the roof
installation.

This particular garage has two different roof systems. The front half (parking area) uses prefabricated
trusses which allow for an attic storage area. The second half (working area) uses a traditional rafter
system. Because our rafter system includes the roof over the "shop" area which has a different angle this
rafter system will have a peak ridge beam and another support beam where the main garage and "shop"
roofs come together. If this is a little confusing, don't worry.... all will become clear in the next couple
weeks as you see the roof in this section come together.
In order to make building the 3 gable ends a little easier, one of the trusses was used as a template. Here
the truss is supported by saw horses and the 2x6 framed gable end is built right on top of the truss. Care
must be taken when building gable ends because not all are going to be exactly the same size as the trusses.
In our case the front and rear gable ends are actually 3 1/2" (the width of a 2x4) shorter than the trusses.
This is to allow for the out lookers which mount the front and rear fascia. The center gable is exactly the
same size as the trusses since there will be no out lookers where the two roof systems meet.
Once the gable has been framed we removed it from the truss and leaned it up against the center wall to
make room for the next one. The gable you see here is the front gable end and is not complete in this
picture. Shortly after this photo was taken the framing for the window was added which completed the
structure.
The center gable must have a pocket for the LVL ridge beam. In this case the beam is 3 1/4" wide, 16 1/4"
tall, and 27 feet long.
Two down and one to go. When the last gable is framed we will lay them down on the floor and sheet each
one with 1/2" OSB. Anyone want to help lift them up to the top of the walls?
Here is a composite photo just for the "car guys". This photo gives you a good look at the two 18x8 foot doors. The
front half (parking area) is 25' deep. The back half (working area) is almost twice as deep and just as wide. Eat your
heart out fellas.

Once complete the garage will be covered with log siding. The log siding provided by Kuhns Brothers will make the
garage indistinguishable from the rest of the house. You simply won't be able to tell where the real logs stop and the
log siding on the garage begins.
That's it for another week. Next week big things will happen. Wednesday we will
have our roofers back and a crane will be here to lift the gable ends, beams, and
trusses into position. The roofers will then sheet the front half of the garage roof.
We'll be busy the rest of the week installing the rafters in the "shop" and working
areas of the garage as well as the bonus room above the kitchen. It's going to be a
busy week.
Check back soon.